City of Cleveland -  Division of Water
Capital Improvement Program
Future Contract Award Schedule (1999 - 2008)
Estimated
Project Cost
PROGRAM MANAGEMENT @ WATERWORKS PLANTS
Program Management - Phase II 18,000,000
Program Management - Phase III 10,000,000
sub-total 28,000,000
BALDWIN PLANT IMPROVEMENTS
Filter Rehabilitation - Phase I 37,000,000
Administration / Chemical - Phase I 29,000,000
Rapid Mix 12,400,000
Pretreatment 52,800,000
Residuals and Reservoir 11,100,000
Fairmount Pumps & Building Improvements 26,600,000
Kirtland Pumps, Electrical & Building Modifications 26,600,000
sub-total 195,500,000
CROWN PLANT IMPROVEMENTS
Low Voltage Electrical 1,600,000
Sludge Dewatering Building Rehabilitation 1,800,000
sub-total 3,400,000
MORGAN PLANT IMPROVEMENTS
Pump Station 38,600,000
East & West Reservoirs 54,300,000
Chemical Facility 16,300,000
Intake Improvements 6,800,000
Residuals, Pretreatment, Raw Water Pumps 35,300,000
Filter Rehabilitation 35,500,000
Division Avenue Relocation 3,400,000
Switchgear Protection at Morgan F.W. Station 60,000
sub-total 190,260,000
NOTTINGHAM PLANT IMPROVEMENTS
Filter Rehabilitation - Phase I 22,200,000
Chemical - Phase I 19,800,000
Pretreatment Improvements 18,900,000
Backwash Clarifier 4,200,000
Residuals System Upgrade 7,600,000
Administration Building 7,100,000
Pump Rehabilitation 20,200,000
Reservoir Rehabilitation 24,400,000
Replacement of Pump Station Roof 710,000
Boiler Replacement 410,000
sub-total 125,520,000
MISCELLANEOUS PLANT IMPROVEMENTS
Overall Plant Instrumentation 9,200,000
Security - All Plants 4,100,000
Rehabilitate Chlorine Cylinder Cranes 190,000
Rehabilitate Fairmount, Kirtland & Nottingham Cranes 360,000
Fence Improvements @ Nottingham, Morgan & Parma 710,000
sub-total 14,560,000
SUPPLY MAINS
Bagley/Fitch Road Water Main 2,100,000
Cohran/Harper Water Main-Section I 2,800,000
Innerbelt Bridge Water Mains Reinsulation 2,300,000
Kinsman-Green Water Main 3,500,000
North Royalton - Broadview Supply Main - Phase II 14,000,000
Sheldon Road Water Main 3,500,000
Warrensville-Broadway Water Main-Section II 9,400,000
Water Main Repairs Special 2,800,000
sub-total 40,400,000
DISTRIBUTION MAINS
Distribution Main Replacement Program 18,000,000
sub-total 18,000,000
CLEANING AND LINING WATER MAINS
Cleaning & Lining - Distribution Main Program 54,000,000
Cleaning & Lining - Trunk Main Program 2,000,000
sub-total 56,000,000
SECONDARY STATION IMPROVEMENTS
Annual Painting / Towers and Tanks 14,700,000
Bagley Road Tower 4,240,000
Broadview Road Pump Station 5,000,000
Broadview Road Tower 1,500,000
North Royalton 4th High Pumps 700,000
Parma Pump Station Second Power Supply 1,800,000
Parma Reservoir Renovation Project 10,000,000
Pump Replacement - Various Stations 5,600,000
Secondary Station Re-Chlorination Facilities 1,150,000
Strongsville Tower Drainage Improvements 650,000
sub-total 45,340,000
BUILDING AND TECHNOLOGY IMPROVEMENTS
1440 Lakeside Purchase & Renovations 10,300,000
Cathodic Protection Program 750,000
CIP Professional Services - Testing 4,000,000
City-wide GIS 26,000,000
Harvard Yards - Phase V (Security) 500,000
Water Audit Implementation 4,000,000
sub-total 45,550,000
CLEVELAND ROADWAY PROJECTS
Various City of Cleveland Roadway Projects 10,655,000
sub-total 10,655,000
UNDEFINED CAPITAL PROJECTS
Undefined future capital projects allocations (2003-2008) 135,000,000
sub-total 135,000,000
TOTAL 908,185,000